San Anselmo Flood Risk Reduction Project schedule

Milestone Timeline
Final Environmental Impact Report certification hearing at District Board of Supervisors meeting September 2018
BB2 building demolition completed June 2020
Flood Diversion and Storage Basin Part 1 Construction completed November 2020
90% engineering design plans February 2021
Permit Approval Spring 2021
100% design plans for Flood Diversion and Storage Basin July 2021
Flood Diversion and Storage Basin Part 2 Construction bidding and award Spring/summer 2021
Flood Diversion and Storage Basin Part 2 Construction September 2021 to October 2022
100% design plans and specs for BB2 project March 2022
BB2 construction bidding, award, and construction Summer/fall 2023
BB2 flood mitigation design and construction TBD