Category: San Anselmo Flood Risk Reduction Project
In light of a clarification received this week from the Federal Emergency Management Agency (FEMA), the Marin County Flood Control and Water Conservation District announced a postponement for removing Building Bridge 2 (BB2) from the creek in downtown San Anselmo. As recently as last week, the District felt the bridge removal could proceed later this … Continued
The Marin County Flood Control and Water Conservation District will be hosting a Community Informational Open House about the San Anselmo Creek Bridge removal (BB2) on January 11, 2024, from 6:30 p.m. to 8:30 p.m. at the San Anselmo Town Council Chambers, located at 525 San Anselmo Avenue. During this two hour open house, you … Continued
Revised Notice of Availability Addendum to 2018 Environmental Impact Report (EIR) for the San Anselmo Flood Risk Reduction Project (Building Bridge #2) Project Location: 634-636 San Anselmo Ave., San Anselmo, CA Project Contact: Hugh Davis, Civil Engineer | (415) 473-4232 | envplanning@marincounty.org Project Summary: *Please note* The public review period for this notice has … Continued
The Marin County Flood Control & Water Conservation District has been working for the past several years on the San Anselmo Flood Risk Reduction (SAFRR) Project, which is a significant effort to protect lives and property during severe storms. In 2018, the Board of Supervisors certified the Environmental Impact Report (EIR) for the Project. … Continued
Work is progressing nicely with the detention basin at the former Sunnyside Nursery, located at 3000 Sir Francis Drake Boulevard. It is nearing completion and it will be operational this rainy season. Once completed, the detention basin will hold stormwater overflows from Fairfax Creek during peak storm events by having water spill over a side … Continued
Development part of larger flood mitigation and public safety project near Fairfax The final phase of the Marin County Flood Control and Water Conservation District’s Sunnyside Flood Detention Basin project is expected to begin in August with a goal of improving public safety for properties along Fairfax Creek and San Anselmo Creek in the upper Ross … Continued
Final phase of stormwater basin moving forward despite bridge project issue The Marin County Flood Control and Water Conservation District is wrapping up plans for the final phase of the Sunnyside Stormwater Detention Basin and the project is expected to open for contractor bids this summer. The basin, located at 3000 Sir Francis Drake Boulevard … Continued
The first part of the Sunnyside Detention Basin construction was completed ahead of schedule in mid-November. Work included demolition of all the existing buildings and structures, stripping and stockpiling gravel and topsoil to be re-used at the site, and excavation and off-haul of approximately 20,000 cubic yards of earth. The site was covered with mulch … Continued
Excavation of the Fairfax flood control basin set to start in September The Marin County Flood Control and Water Conservation District will begin excavating Sunnyside Basin near Fairfax in early September as part of the San Anselmo Flood Risk Reduction Project. The excavation and relocation of 20,000 cubic yards of earth is expected to take … Continued