Deer Island Basin Tidal Wetlands Restoration Project

About

The District’s Deer Island Basin Complex is located in the lower Novato Creek watershed. The proposed project area includes two stormwater ponds (Ducks Bill and Herons Beak) along the south side of Novato Creek as well as the Deer Island Basin on the north side of Novato Creek.

Since 2021 the project team has actively consulted the San Francisco Bay Restoration Regulatory Integration Team. This included site tours with key regulators and multiple rounds of project design discussion and comment. Soliciting early input from regulators has been an asset to informing the project’s permitting approach.

Project Goals

  • Restore floodplain and tidal connectivity to diked historic tidal wetlands along Novato Creek, restoring tidal wetland habitats
  • Enhance ecological functions within baylands habitats along/adjacent to Novato Creek
  • Preserve and improve habitat conditions that support special status species known to occur, currently and/or historically, within Novato Creek and associated tidal marshes
  • Contribute to long term flood control goals and sea level rise resiliency for the lower Novato Creek Baylands
  • Protect critical infrastructure located within and adjacent to the project area by maintaining or increasing current levels of flood protection

Project map

map of the Deer Island project area

Timeline

Design and environmental compliance, including CEQA and permitting, will be completed by summer 2023.

Status:

The project team is currently completing the Preliminary Design Report to produce 50% project designs. These designs will inform analysis of the project's impacts under CEQA and further refine project construction cost estimates.

Funding

To-date, the District has secured $630,000 in Measure AA grant funding for this project. These grant funds cover project design, environmental review, and permit applications.

In December 2021, the Marin County Board of Supervisors allocated $2,000,000 of American Rescue Plan Act funds toward the project construction. Additional construction funding will need to be identified and secured, with cost estimates being refined under the current design process.

Zone

Zone 1: Novato

Agencies and partners

  • Marin County Flood Control and Water Conservation District
  • San Francisco Bay Restoration Authority
  • Environmental Science Associates

Contact

Close window