Marin City Pond Flood Reduction Project

About

The purpose of the Marin City Pond Flood Reduction Project is to make several improvements to the stormwater drainage and pond system . This includes a new pump station at the pond to improve drainage out of the pond to the bay.

The initial plan was for a trenchless installation of the culvert. After further geotechnical analysis in August 2021, this approach was found to be technically infeasible. Issues around the subsurface soils make trenchless installation risky and prone to failure.

The project team developed a new design with a pump station  and flood wall  at the edge of the pond that uses the existing pipe under US 101 to drain flood waters. These proposed improvements reduce flood risk under current and sea level rise conditions as compared to existing conditions

Timeline

A contract for design, permitting and environmental analysis for the pump station project is currently slated to be awarded on September 19, 2023. Draft design will likely be completed around the end of 2024, and CEQA and NEPA in 2025.  Construction could occur as early as 2026, depending on environmental review needs.

Funding

The budget for design, permitting and environmental analysis contract is $883,636.

The estimated cost for the revised project scope is approximately $10 million and the District is working with FEMA to help fund this project.

Zone

Zone 3: Richardson Bay

Agencies and partners

  • Marin County Flood Control & Water Conservation District
  • California Office of Emergency Services (CalOES)
  • Federal Emergency Management Agency (FEMA)
  • Audubon California
  • Marin City Climate Resilience and Health Justice
  • Marin City Community Service District

Contact

Close window